One of the biggest frustrations for UK businesses investing in a leased line is the installation time. Unlike broadband, leased lines require dedicated fibre, planning permissions, and sometimes civil works — which means installs don’t happen overnight.
So how long does it actually take? And do some providers deliver faster than others?
Typical Leased Line Lead Times
Across the UK, the average installation time is 45–90 working days. This varies depending on:
-
Whether fibre is already in place near your building.
-
If wayleave (landlord permission) is required.
-
Which provider is delivering the circuit.
Some installations are quicker — but if wayleave or extra construction is needed, the process can stretch longer.
Provider Differences
-
BT: Nationwide coverage means they’re often the only option in rural areas. Lead times can be quicker where infrastructure already exists, but longer if new digs are required.
-
Virgin Media Business: Strong in cities; installations are smooth in metro areas but may involve delays outside of their core footprint.
-
CityFibre: Often faster in urban centres where their network is live, as they control their infrastructure end-to-end.
-
Vorboss: In London, installs can be rapid thanks to dedicated local fibre builds.
-
ITS (Faster Britain): Focused on underserved areas, often delivering faster than expected in regions where they’ve invested heavily.
See exactly which providers can deliver quickly in your postcode with our leased line providers comparison tool.
What Can Delay an Install?
-
Wayleave Agreements: If you rent your premises, the landlord must give permission to run fibre into the building.
-
Excess Construction Charges (ECCs): If major digging is required, it can add time (and sometimes cost).
-
Streetworks & Permits: Local authority approval may be needed for digging up roads or pavements.
At Connect2, we flag these issues early so you know exactly what to expect.
How to Speed Things Up
-
Submit paperwork quickly: Wayleave forms and landlord approvals are often the biggest bottleneck.
-
Plan ahead: If you know your current contract ends in 3–6 months, start the leased line order now.
-
Work with a partner: Connect2 manages the whole process — chasing providers, coordinating engineers, and keeping you updated.
Why Lead Times Matter
For businesses moving office, upgrading systems, or scaling cloud usage, every day without connectivity is costly. Knowing realistic timelines helps you plan transitions without downtime.
Get clarity today — request a leased line quote and we’ll show you both the pricing and the estimated lead time for every available provider.
Final Thoughts
While leased line installations typically take 45–90 days, the actual timeline depends heavily on the provider, your location, and whether extra construction is needed.